Designer Header
Reviving a Waterfront,
Reconnecting a City

A 20-acre urban park now connects Seattle’s downtown to its world-class waterfront

DESIGNER

2025

Seattle’s downtown has a new front porch — a 20-acre urban park that redefines the city’s connection to its iconic waterfront. The shoreline is now a vibrant, welcoming space that celebrates Seattle’s culture, history and natural beauty.

With the completion of the Alaskan Way State Route 99 Tunnel in 2019, the city seized the opportunity to reimagine its waterfront — not just as a corridor for movement, but as a destination for people. This transformation is the result of a landmark effort led by the City of Seattle’s Office of the Waterfront, Civic Projects and Sound Transit.

“You look one direction and you can see the city’s skyline. Turn around, and you are met with the beauty of Elliott Bay, the Olympic Mountains to the right and Mount Rainier to the left,” said Paul Huston, HNTB program manager. “It’s breathtaking, and now the waterfront redevelopment opens up this clear view — this is the front porch Seattle has wanted for generations.” 

Designing Seattle’s new front porch

Planning for the waterfront transformation began in 2009, launching a multiyear process that included extensive environmental reviews, a worldwide design competition and the input of more than 10,000 residents. The result: nearly 20 major projects valued at $1.2 billion that define one of the largest civic redevelopments in Seattle’s history.

The city’s Office of the Waterfront, Civic Projects and Sound Transit grouped nine of those projects into one construction management program, supported by a joint venture team, including HNTB, that began construction in 2018:

Slide

Before construction started on this program, the city built a new seawall to meet current seismic standards, protect public safety and act as the foundation for Seattle’s new waterfront.  

“Together, our Waterfront Seattle projects represent the single most important transformational program in Seattle in 100 years,” said Angela Brady, PE, director of the City of Seattle’s Office of the Waterfront, Civic Projects and Sound Transit.

Recognizing the scale and complexity of the waterfront transformation, city leaders in 2018 adopted their first programmatic construction management approach to guide its delivery. 

“They wanted experienced professionals working on downtown Seattle projects and major construction programs who they could trust and who could adapt across multiple complex projects constructed over many years,” Huston said. “The city wanted people with the right mindset who would serve as an extension of the city’s team — and HNTB delivered.” 

The joint venture team colocated with the Office of the Waterfront, Civic Projects and Sound Transit, working seamlessly as one unified team to deliver one of the most logistically demanding urban infrastructure projects in Seattle’s history.

“We brought the right expertise at the right times over seven years,” Huston said. “Our field and office team could adapt and scale to meet changing needs, with many members cross-trained to fill multiple roles. That continuity provided efficiency, familiarity with all the important details and made a big difference in delivering this program.”

Angela Brady

“Together, our Waterfront Seattle projects represent the single most important transformational program in Seattle in 100 years.”

– Angela Brady
Director of the City of Seattle's Office of the Waterfront,
Civic Projects and Sound Transit
Paul Huston

“You look one direction and you can see the city’s skyline. Turn around, and you are met with the beauty of Elliott Bay, the Olympic Mountains to the right and Mount Rainier to the left. It’s breathtaking, and now the waterfront redevelopment opens up this clear view — this is the front porch Seattle has been missing for generations.”

– Paul Huston
HNTB Program Manager
previous arrow
next arrow

Keeping the city moving

The seven-year construction program unfolded in multiple stages, with several projects overlapping in both schedule and location. At its peak, seven projects were underway simultaneously — amid the bustling activity of an operational ferry terminal, seasonal cruise ship arrivals that tripled tourist traffic, active utilities, ongoing private construction, waterfront businesses and daily residential life. 

Throughout the construction phase, the city prioritized accessibility, integrating requirements into construction contracts to ensure pedestrians, cyclists and vehicles maintained access to the waterfront and one of the busiest ferry terminals in the nation.

“The new main corridor was being built alongside new buildings and parking garages,” said Brian Kittleson, HNTB construction engineer. “We coordinated closely with those private developers and held regular meetings with the city’s permitting agency to manage traffic routing, work impacts and detours — not just for our site, but across the entire area.”

Sustainable Seattle

 

The waterfront transformation includes:

  • Salvaged Ekki wood from the old Alaskan Way seawall repurposed as handrails
  • A restored 100-year-old pergola building now home to new businesses and art installations by local artists that celebrate Seattle’s heritage. 
  • 1,000 new trees
  • 100,000+ new plants
  • Natural stormwater treatment system filtering 95% of runoff 

Puzzle solved through coordination

A particularly complex site within the program involved the convergence of three major projects: Overlook Walk, Alaskan and Elliott Ways and a public-private expansion of the Seattle Aquarium. Coordinating these overlapping work zones required close collaboration among contractors, city agencies and the community to manage shifting schedules, competing demands and evolving site conditions. 

“When all those schedules moved around and changed, our construction management team was able to put the puzzle pieces back together in unique and creative ways to fulfill the goal of doing as much as possible in a short time while maintaining public access and mobility,” said Jessica Murphy, construction program manager of the City of Seattle’s Office of the Waterfront, Civic Projects and Sound Transit.

Throughout construction, proactive communication was vital. 

“Having a team familiar with construction sequencing and the constraints of technically challenging projects was key,” Brady said. “This helped us translate technical details into clear information that residents and businesses could best understand, building trust and support.”

A waterfront for all

The transformation of Seattle’s waterfront is more than a construction success — it’s a civic reinvention. From better mobility and accessibility to vibrant public spaces and iconic views, the program delivers on a decades-old promise to reconnect the city with its shoreline.

“It’s mind-blowing to see how close our construction results are to the original vision and concept design renderings,” Brady said. “Seattle rebuilt our waterfront and stitched our downtown back into it, so people could enjoy Elliott Bay, the Olympic Mountains and all the waterfront has to offer.”

With every trail, terrace and transit connection, the new waterfront signals not only a feat of engineering and urban design, but a lasting legacy of civic ambition — one that will serve generations of Seattleites and visitors to come.

“We created a waterfront that serves a variety of people and uses. Everyone wants to be down here. It’s just as we envisioned: a waterfront for all,” Murphy said.

CONTACT

Paul Huston

HNTB Program Manager

(512) 750-0310

[email protected]

 

Brian Kittleson

HNTB Construction Engineer

(206) 819-5715

[email protected]

 

Kris Mason

HNTB Program Controls Manager

(310) 614-3152

[email protected]

SEE MORE ARTICLES

MORE DESIGNER STORIES

Designer Magazine

Caltrain Electrification

A New Era

Sound Transit's East-West Extension

Extending East

Lynnwood Link Extension

Linking Communities

MTA's ADA-Compliant Modernization

Accessibility for All

 

Redmond Technology Station Bridge

Transformative Pathway